#ALookBackOn | CLN Data Centre, Co. Meath This week we are reflecting on a landmark project we were proud to be part of: the CLN Data Centre in Meath, Ireland delivered across multiple phases. ✅ ð�—£ð�—µð�—®ð�˜€ð�—²ð�˜€ ð�Ÿ & ð�Ÿ® Delivered large-scale infrastructure works including: – 400,000m³ excavation & 500,000m³ fill – 220km of ducting (fibre, MV, LV, lighting & security) – 4.5km watermain & drainage networks – 450+ precast utility chambers – Roads, pavements & extensive concrete works – Generator yards, loading docks & attenuation ponds ✅ ð�—£ð�—µð�—®ð�˜€ð�—² ð�Ÿ¯ Comprehensive groundworks, utilities & concrete to support a standalone data facility: – 28,000m² floors & 10,000m² generator yard slabs – 480 foundations & 1.2km precast ground beams – Utility infrastructure inc. fibre, MV/LV ducting, drainage & 1.6km watermain – 80 precast chambers – Ancillary in-situ works to electrical, tank & dock areas – Delivered in a live data centre environment with ecological & operational constraints ✅ ð�—£ð�—µð�—®ð�˜€ð�—²ð�˜€ ð�Ÿ± & ð�Ÿ² Civil engineering packages for the final phases of this flagship data centre including: – 450,000m³ excavation & 380,000m³ fill – 200km ducting network & 3.5km watermain – 250 precast chambers, roads & pavements – 1,050 foundations, 4.2km precast ground beams & 60,000m² floors – Generator yards, attenuation ponds & extensive site development works Across all phases, our delivery focused on precision, scale & coordination, supporting the expansion of one of Europe’s leading hyperscale data centre campuses. A huge credit to all teams involved in safely delivering complex works in a live, fast-paced environment🙌